Fire Apparatus Purchase Change Orders

Summary

Long post-pandemic lead times for fire trucks mean specs go stale before delivery, forcing change orders. The city is paying today's prices to fix items — like a required deck gun — that were dropped years ago, though an engine credit should offset much of the 2027 truck's cost.

At a glance

Total mentions
2
Last 30 days
2

Discussed at 1 meeting in the last 60 days; most recently Oct 26, 2026.

Impact analysis

💰Financial impact

About $69,600 added across three trucks, with an engine credit expected to offset a substantial part of the 2027 pumper's $33,461 change order.

✅Who benefits

Appleton firefighters get safer, easier-to-decontaminate trucks that are better equipped for fires and EMS calls.

⚠️Who could be affected

Taxpayers absorb the added cost, partly because an NFPA-required deck gun was dropped from the original spec with no explanation.

Mentions & discussions (2)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Appleton

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.