Lindbergh Standpipe recoating cost reduction
Summary
The city budgeted for inspection and repairs of the Lindbergh Standpipe's interior coating, but the inspection showed repairs would be limited. The engineering contract was cut from $51,465 to $7,343, saving roughly $44,000.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 9, 2026.
Impact analysis
Saves about $44,122 from the budgeted contract amount.
Appleton water utility ratepayers benefit from the savings.
Mentions & discussions (2)
Utilities Committee — June 9, 2026
The city budgeted for inspection and repairs of the Lindbergh Standpipe's interior coating, but the inspection showed repairs would be limited. The engineering contract was cut from $51,465 to $7,343, saving roughly $44,000.
Finance Committee — February 23, 2026
$54,038 is being shifted within the water utility budget to recoat the Lindbergh Standpipe — routine maintenance that keeps the water tower in good shape.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Appleton
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.