Bellaire Court and Glendale Avenue Reconstruction

Parking changes for the Bellaire Court project and ordinance changes for the Glendale Avenue rebuild are on the agenda.

1 mention (1 this month)Last discussed Nov 4, 2026
LowRoads

Final contract payments on city projects

Staff presented closing payments on three finished contracts: $30,000 for sidewalk sawcutting, $6,588.32 for pond dredging, and $70,479.48 for parking ramp repairs totaling about $1.39 million.

1 mention (1 this month)Last discussed Oct 12, 2026
LowRoads

Overnight construction noise variance — South Badger

DPW got a narrow variance to run work overnight (5 p.m.–7 a.m.) for two consecutive days the week of June 1 on the 200 block of South Badger. Residents nearby may hear construction at night.

1 mentionLast discussed May 13, 2026
LowRoads

French Road paving scope reduction

The concrete paving contract shrank by $160,114.80 because an east-side path on French Road is on hold until utility conflicts and coordination with neighboring municipalities are resolved — but expect it to come back later.

1 mentionLast discussed May 11, 2026
LowRoads

TIBA ramp access upgrades

An extra $67,000 for TAPCO covers upgrades to TIBA ramp access equipment, bringing that contract to $288,209.

1 mentionLast discussed Mar 9, 2026
LowRoads

N. McDonald Street Parking Changes

After a six-month evaluation, the council approved parking changes on the 1500 block of N. McDonald Street.

3 mentionsLast discussed Feb 18, 2026
LowRoads

Canal Street vacation

The city gave up its right-of-way on the southern half of Canal Street, 120 feet west of S. Lawe Street — part of redevelopment activity in that area.

2 mentionsLast discussed Jan 21, 2026