Bedford Road & S. Grandview Road reconstruction
Summary
The reconstruction contract went to Northeast Asphalt for $397,527.45 — the low bid — with work wrapping up this construction season.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 2 meetings in the last 60 days; most recently Sep 30, 2026.
Impact analysis
The city is paying $397,527.45 for the reconstruction work.
Residents of Bedford Road and S. Grandview Road get rebuilt streets.
Residents may face temporary construction disruption and detours.
Mentions & discussions (3)
Improvement and Services Committee - Sep 30, 2026
The reconstruction contract went to Northeast Asphalt for $397,527.45 — the low bid — with work wrapping up this construction season.
Improvement and Services Committee - Sep 9, 2026
With bids opening September 15 and the construction season ending, the committee let staff award this road project directly so work can still happen this year.
Improvement and Services Committee - May 13, 2026
The city is paying $69,555 for engineering design of reconstructing Bedford Road (converting it from gravel to pavement) and a stretch of South Grandview Road that has pavement damage from utility work. Design is funded in the capital budget.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Green Bay
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.