TID 35: 200 N Monroe timeline delay

Summary

The 168-unit workforce housing TID is on hold at the developer's request. The base year shifts to January 1, 2027 to match a slower construction schedule caused by soil issues and power-line relocation work with WPS.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Aug 25, 2026.

Impact analysis

💰Financial impact

Delaying the base year means the TID captures increment starting in 2027, maximizing available increment once construction begins in spring.

✅Who benefits

Future workforce-housing residents and the developer, who gains time to resolve site issues.