18 issues in water utilities

LowWater Utilities

Water Treatment Chemical and Park Structure Bids

The city is soliciting bids for ferric chloride and polymer, chemicals used to remove phosphorus from water, plus bids for a Mindiola Park structure.

1 mention (1 this month)Last discussed Nov 5, 2026
LowWater Utilities

Utility transformer placement in Winterberry Reserve Phase 2

A new We Energies policy forced transformers into front yards, prompting a relief request. The developer scaled back to just three transformers with landscaping required to soften their look.

1 mention (1 this month)Last discussed Oct 28, 2026
MediumWater Utilities

UPS purchase for new Operations Center

The new operations center is nearly done, with the office move set for December 2 and reopening December 3. Consolidating buildings should eventually trim costs, though the larger new facility may cost slightly more to operate at first.

2 mentions (1 this month)Last discussed Oct 20, 2026
HighWater Utilities

Clean Water Plant sand filter defects

The city's wastewater plant scored a perfect 4.0 on its state compliance report for the tenth year running, even weathering a 200-year rain event. A sludge dryer project will turn plant solids into a DNR-approved Class A biosolid product the public could eventually purchase.

2 mentions (1 this month)Last discussed Oct 8, 2026
MediumWater Utilities

Area 10 floodplain project BRIC grant

The neighborhood near University/Algoma deals with flooding. A new $191,000 federal grant (city share $64,000) funds detailed design; construction could come around 2029 if another grant lands.

1 mention (1 this month)Last discussed Oct 8, 2026
MediumWater Utilities

One-time sewer credit program and ordinance revision

The board split on sewer credit requests — approving four homeowners' credits but denying two whose projects didn't count as 'new landscaping.' Vice Chair Kevin Reilly referred the murky Chapter 29.11 rules to the O&L Committee for a cleanup, so expect clearer eligibility standards soon.

2 mentionsLast discussed Sep 17, 2026
MediumWater Utilities

Water utility cybersecurity

The commission discussed protecting the water utility's computer systems from potential cyberattacks behind closed doors, following recent incidents at other water systems.

1 mentionLast discussed Sep 17, 2026
HighWater Utilities

Deer Path flood mitigation timing

Residents of the Deer Path subdivision begged the committee to speed up flood mitigation construction from 2028 to 2027, describing repeated basement flooding and boat rescues. Staff say design, utility coordination and grant timing make 2028 realistic.

3 mentionsLast discussed Sep 8, 2026
HighWater Utilities

Patrick Ponds and Summit Woods Pond Rehabilitation

The city is spending about $2.5 million to rehabilitate two neighborhood stormwater ponds, keeping drainage working and reducing flood risk. The low bid from C.W. Purpero, Inc. was recommended for award.

2 mentionsLast discussed Sep 1, 2026
MediumWater Utilities

Hawk's Landing stormwater maintenance

Amendment No. 1 with McMahon Associates continues vegetation management services for the city's stormwater facilities.

2 mentionsLast discussed Aug 20, 2026
HighWater Utilities

Pump stations improvement project

The city awarded a $2.08 million contract to Mid City Corporation to replace the Ruben Drive sanitary pump station — key sewer infrastructure for that neighborhood.

3 mentionsLast discussed Aug 4, 2026
MediumWater Utilities

Lead and copper sampling

Lead and copper sampling is underway with about 30 residents helping, including commissioners. Results feed regulatory compliance for the water system.

1 mentionLast discussed Jul 16, 2026
MediumWater Utilities

Water utility wells and Prairie Avenue main

Pumps are out of wells 5, 6, 11, 12 and 13, with gravel fill underway — well 5 was dynamite-blasted years ago, making abandonment trickier. Demolition of the well 5 and 6 structures goes out to bid July 21 with bids opening August 11.

2 mentionsLast discussed Jul 16, 2026
MediumWater Utilities

New Operations Center construction costs

The new Operations Center is coming along — geothermal wells drilled, brick and garage doors going in, offices drywalled. Commissioners may tour the building before the next meeting, and a $38K battery backup was just added to the project.

3 mentionsLast discussed Jul 16, 2026
HighWater Utilities

Backyard main letters — Hine, Glenn, Cumberland and Summit

Dozens of homes have water mains running through their backyards without proper easements, and the city attorney's office says the utility must fix it — moving mains, reconnecting services, and making homeowners whole. Expect letters to residents, years of phased construction, and costs borne by ratepayers.

2 mentionsLast discussed Jul 16, 2026
LowWater Utilities

Williams Street underground electric conversion

Overhead electric lines on Williams Street will be placed underground under a $99,920 contract with Bevara, improving reliability and appearance on the street.

1 mentionLast discussed Jun 16, 2026
MediumWater Utilities

Transit Center passenger signs

Eight electronic bus bay signs and a lobby arrivals monitor return after being removed during ceiling work, adding audio and braille features for visually impaired riders.

1 mentionLast discussed May 21, 2026
HighWater Utilities

Burr Oak Boulevard sewer repair and lining

A sewer main on Burr Oak Boulevard failed during last August's floods. An emergency repair was completed, and the board has now awarded a contract to line and reinforce the rest of that section so it doesn't fail again.

1 mentionLast discussed May 21, 2026