Wastewater Treatment Plant Building R Renovation
The renovation of a 1930s building at the wastewater plant came in over budget, so the committee recommended shifting $100,000 from an under-budget roofing project and awarding a $172,600 contract to RJM Construction. The building will consolidate equipment storage.
Stormwater projects and rate analysis
The Veterans Memorial Park pond expansion is funded for 2027 using carried-over and new funds, the Oneida Street Bridge replacement is queued, and staff say a stormwater rate analysis is needed within the next year — big flood-control projects will likely push rates up.
Lead Water Service Line Replacement
Appleton is hiring a consultant to educate residents about its lead service line replacement program and how to participate. If your home may have a lead service line, this campaign is how you'll learn about the program and sign up.
Water Main Breaks, April-June 2026
The committee reviewed two months of water main break reports and a Water Supply Service Plan for Appleton Water Works — both pointing to ongoing needs in an aging water system.
Paratransit rider app and fare payment upgrades
A $50,000 budget line will fund a new app for paratransit riders to schedule trips — something customers have been asking for. The WISCO fare system may also add open payment (credit card, phone) in 2027, mainly helping occasional riders.
Utilities Network System Upgrades Project
The city is buying roughly $632,000 in network equipment — Wi-Fi, phones, and the SCADA utility control system — through a sole-source state contract with Heartland Business Systems, which recently completed a similar city project under budget.
Mini sewer program one-property connection
A permitting error let one homeowner build expecting a public lateral that wasn't scheduled, so the city is spending $21,950 to connect him this year — raising fairness questions from alderpersons about other waiting residents.
Storm sewer lining near St. Mary's Cemetery
An aging storm sewer running through a ravine to the river will be lined rather than replaced, timed with St. Mary's Cemetery bridge removal project that will put 10 feet of fill over the pipe.
Unit J-26 Mini Storm Sewer Bid Rejection
The only bid for a small storm sewer project came in at $347,720 versus an expected ~$200,000, so the committee backed rejecting it. Drainage improvements, including backyard drainage fixes in older subdivisions, will wait about a year while the city repackages the work.
Northland-Bellaire Flood Study
The council took the next step on a multi-year, roughly $22 million, three-phase plan to cut catastrophic flooding in the Northland–Bellaire area — from over five feet of flooding in a 100-year storm down to about half a foot. All ratepayers will share the cost through stormwater fees, but Ald. Croatt and Meltzer framed it as a sound infrastructure investment for the hardest-hit neighborhoods.
Wastewater treatment plant upgrades and paving
The committee recommended buying two digester circulation pumps ($57,640) and a $423,000 truck scale paving project at the wastewater treatment plant — routine but essential spending to keep the plant running.
Utilities Department reorganization
A vacant utilities position is being retitled from treatment specialist to process specialist and will report to the deputy director, focusing on technical work. It costs nothing extra — same pay grade.
Utilities network and SCADA infrastructure upgrades
A $698,201 contract with Van Ert Electric modernizes the wastewater utility's aging business network, phone system and Wi-Fi, laying groundwork for a much larger SCADA upgrade in a couple of years.
Flood mitigation property acquisition services
The city wants a consultant ready to help buy property that could improve flood control project designs. Nothing is being purchased yet — engineering feasibility work is still underway — but this $221,500 contract gets the expertise in place. Stormwater utility funds cover it, not property tax dollars.
W-25 Sewer & Water Reconstruction No. 2 closeout
The city awarded a $2.77 million contract to Kruczek Construction to rebuild sewer and water infrastructure — the largest spending item on the night's consent agenda.
Perfect 4.0 state compliance score for wastewater utility
Appleton's wastewater utility earned a perfect 4.0 grade on the state DNR's annual compliance report, reflecting strong treatment and maintenance performance. The committee forwarded a resolution to the council committing to continued investment in the facility.
Lindbergh Standpipe recoating cost reduction
The city budgeted for inspection and repairs of the Lindbergh Standpipe's interior coating, but the inspection showed repairs would be limited. The engineering contract was cut from $51,465 to $7,343, saving roughly $44,000.
Wastewater Treatment Facility Master Plan
The city's wastewater treatment plant is nearly 40 years past its last master plan and is arguably the city's most critical long-term facility. This contract funds the study that will guide major investment decisions for decades.
Water treatment plant equipment purchase
A small $8,000 contract addition keeps the water treatment plant's bulk hypochlorite tank replacement project on track for design and construction management.
Anaerobic Digester Improvements
The wastewater utility is spending up to $1.7 million to inspect, maintain, and upgrade its anaerobic digesters, using carried-over prior-year utility funds.
Wastewater Digester Improvements
The council awarded a roughly $1.7 million contract to inspect and upgrade the wastewater treatment plant's anaerobic digester, core infrastructure for processing sewage. The work is funded through wastewater utility budget carryovers.
Duplex water service code amendment
A proposed change to Section 4-278 of the Municipal Code would update water supply system and water service requirements for duplex buildings. It was recommended for approval and heads to the Common Council.
WisDOT I-41 stormwater detention pond agreement
A memorandum of agreement with WisDOT covering construction and maintenance of a stormwater detention pond, plus a permanent limited easement, was scheduled for action in connection with the I-41 project.
Sewer and water infrastructure investment
K2B Pond Rehabilitation
The city is taking the first design step to rehabilitate the K2B stormwater pond, which helps manage stormwater and reduce flooding. The committee recommended hiring McMahon Associates to design the project for up to $67,371.